Skip navigation
PYHS - Header

Construction of South Facility Wyoming State Penitentiary, WY Department of Administration and Information, 2016

Download original document:
Brief thumbnail
This text is machine-read, and may contain errors. Check the original document to verify accuracy.
STATE OF WYOMING

Matthew H. Mead
Governor

DEPARTMENT OF ADMINISTRATION
AND INFORMATION
Construction Management Division
700 West 21st Street
Cheyenne, WY 82002
Phone: (307)777-7769

Dean Fausset
Director
Mel Muldrow
Administrator

Members of the Task Force:
Per your request, the following is a summary of information and a timeline of events
related to the construction of the South Facility at the Wyoming State Penitentiary:
Key Players
● State Entities
○ State Building Commission: oversight entity/ all contracts in SBC name
○ Governor: Jim Geringer (chief of staff: Rita Meyer)
○ Dept. of A&I
■ Art Ellis & Frank Galeotos: directors (exact dates unknown)
■ Steve Mollenhauer & Mike Abel: A&I General Services
Administrators/ SBC secretary (exact dates unknown)
■ Dave LaPlante: lead project manager
■ Ken Burnett: assistant project manager
■ Daniela Lucero: construction clerk
○ DOC
■ Judy Uphoff: DOC director
■ Doug Shope: former DOC facilities manager
● Contractors:
○ High Country
■ dirt work, water lines, some drains
○ KK Mechanical
■ HVAC, sprinklers
○ Intermountain Electric (IME)
■ Site electrical and building electrical
○ CCC Group
■ signs, doors, some windows
○ Mask
■ security, some fencing
○ Custom Fence
■ Security fencing
○ Groathouse:

AI.WYO.GOV

■ general construction (but not necessarily general contractor) for
south facility, A unit, Central Production Facility (CPF), K unit
■ Project manager: James Mackey, superintendent: Rick Nelson
■ subcontractors: Elco Drilling, Barton Construction, Custom Fence,
Mobile Concrete, others to be determined
○ Kloefkorn/ Ballard:
■ general construction (admin/ warehouse building only)
● Design Professionals
○ Plan One (south facility including A unit, not CPF/ K unit)
■ Subcontractors: Terracon (soils testing, etc.), Bay & Lower
(structural), others to be determined
■ Lead design: Skip Young
○ Tobin (CPF/ K unit)
■ Subcontractors: to be determined
○ Terracon
■ Geo-tech (generally subbed out, but some direct contracts with SBC)
● Bonding/ Funding Entities
○ Wyoming Building Corporation (WBC): quasi-public facility lessor, site
lessee, funding source (i.e. floated bonds to finance construction)
○ Hanihen Imhoff: investment/ bonding team: (also local teams)
○ Kutak Rock: bond counsel (also some local counsel)
○ Wyoming Bank & Trust: trustee/ depository of various bonds and available
construction funds
Key Dates:
● October 1977: BLM grants 640 acres to State for development of penitentiary
● 1980: north facility opens (housed about 500 medium security inmates)
● Late 1980s/ Early 1990s (approximate): State sued by federal Bureau of Prisons
for prison conditions at north facility
● Late 1980s/ Early 1990s (approximate): SBC sues design professional of north
facility
● Early/ Mid 1990s (approximate): re-grouting project undertaken to repair
structural issues at north facility, due to spread footing/ pad design
● October 1995: initial bond counsel & investment bankers’ correspondence with
details of lease revenue bond financing, for south facility construction
○ State will convey title to facilities to public nonprofit corporation (separate
entity from State), which would then lease facilities back to State
○ State must make periodic rent payments subject to appropriations
○ Corporation will issue certificates of participation (through indenture of
trust) in amount equal to sale price, secured by interest on the facilities
AI.WYO.GOV

●

●
●
●

●
●

●

■ Trustee would be assignee of all rights of corporation, and
administer the financing program/ collateral
■ If default, State would have to vacate leased facilities
December 1995: DOC contracts with Criminal Justice Institute for study of prison
needs & capacity
○ Study finds north facility has expanded beyond capacity/ outside of safe
operating conditions
○ Many inmates housed out-of-state at high costs to the State
March 1996: legislature appropriates $41.7 million for new construction, per
section 300(b)(i) of budget bill
October 1996: SBC contracts with Plan One for design services at south facility
December 1996: letter from Plan One to Director Uphoff, explaining information
from soils report
○ Handwritten notes: “Existing prison is spread or pad type [foundation] we
don’t recommend”
February/ March 1997: because of proposed lease bond revenue financing,
legislature removes $41.7 million appropriation for new construction
October 1997: letter from Plan One to LaPlante w/ copy of Terracon proposal for
soils testing
○ Plan One recommends go-ahead, question of direct billing v.
subcontracting
○ Scope of services: evaluate subsurface soil & groundwater conditions,
provide recommendations for foundations, slab, and dirt work
October 1997: original Terracon soils report prepared for Plan One
○ Geo-tech report & recommendations for subsurface soil/ groundwater/
bedrock conditions, foundation/ floor slab/ pavement design &
construction, lateral earth pressures, earthwork, and drainage
○ 23 test borings drilled with groundwater, bedrock & soil testing
○ “Site appears suitable for proposed construction” but expansive bedrock &
soils “will require particular attention in the design and construction”
○ Grade beam/ drilled pier foundation recommended
○ Structurally independent slabs may lessen floor movement due to bedrock
moisture changes
○ If owner selects slab on grade, recommends fill of non-expansive soil &
gravel, isolation joints, contraction joints, and isolation of partition walls
○ Also contains recommendations for surface drainage (including grading)
gutters with 10 foot offset for gutters/ sprinklers, no planters, etc.
○ Recommends Terracon review final design specs for geo-tech issues

AI.WYO.GOV

● November to December 1997: SBC retains investment bankers and private bond
counsel for lease bond revenue financing
● December 1997 to January 1998: SBC selects trustee, approves draft legislation,
approves $47.36 million in lease bond revenue financing (approximately $5million
in capitalized interest), prepares legal documentation for various entities
● February 1998: dirt work addendum from Plan One, includes moisture control
● February to April 1998 (approximate): legislature approves prison bill for lease
bond revenue financing, WBC formed, bonds advertised/ rated/ underwritten
● March 1998: LaPlante hired as A&I’s lead project manager
○ Dave LaPlante required to: (1) act as A&I’s on-site project representative;
(2) review all quality and technical issues with A&I and design
professionals; (3) review all inspection reports, pay applications and other
correspondence with A&I and design professionals; (4) attend pay
application meetings; and (5) provide written progress reports as requested
by A&I.
○ LaPlante was primary State contact point for all construction and design
issues. A&I’s directors/ administrators had a lesser degree of involvement
with day-to-day issues
○ SBC required change order approval/ escalation for higher amounts through
LaPlante, A&I director, then governor
● March 1998 (approximate): HB0054 signed, approving lease bond revenue
financing for south facility
○ Background info: Existing north facility designed for only 541 inmates, but
total statewide prison population of 1,286 as of February 1998
○ Statement of intent: relating to leasing of correctional facility, authorizes
SBC to approve the formation of a Wyoming nonprofit corporation from
which the State may lease prison facilities
○ Authorizes DOC, subject to SBC approval, to execute a lease agreement
with a private party to obtain use of prison facilities
■ DOC cannot pledge state’s full faith/credit for lease payments
■ Lease obligations for State can be terminated if no appropriation
■ Lessor will be a nonprofit corporation, separate from the State, but
its organization is subject to SBC approval
■ Bond financing scheme subject to independent consultant’s review
● March 1998: public AG opinion issued on financing plan, concludes WSP
financing/ legislation did not create an unconstitutional public debt
○ SBC would approve the formation and an initial, self-perpetuating board of
directors of the WBC, a nonprofit entity

AI.WYO.GOV

●

●

●
●
●

●

●

○ State would continue to own the land for the new facility, which would be
leased to the WBC for a 24-year term.
○ The WBC would float 20-year bonds for approximately $72 million in
WSP construction costs.
○ The SBC (through A&I) would construct/ equip WSP for a fixed price, as
part of a construction agreement with WBC
○ WBC would own the WSP facilities, and lease the facilities to the State for
19 years subject to a non-appropriation clause.
○ The WBC would use its lease payments to service the bond debt and
purchase general liability insurance.
○ After 19 years, the State could exercise an option to purchase the WSP
facilities.
March 1998: bid packages opened for south facility, No. E-0144A-I
○ $44.7 million total (with 5% contingency)
○ Dirt work split into phases, Phase I package bid in Feb. 1998, Phase II bid
later
April 1998: SBC approves WBC articles of incorporation & initial organization,
selects board of directors
○ WBC acts as a public benefit corporation under W.S. 17-19-1804
○ Upon dissolution, all assets go to the State
○ State’s default may result in foreclosure on leased facility
○ Substantial completion set for October 2000
May 1998: Groathouse provides proof of liability insurance ($2 million general,
$5 million umbrella)
May 1998 (approximate): dirt work at south facility begins
May 1998 (approximate): WBC/ SBC facility lease executed
○ WBC pays taxes, utilities, general liability insurance
○ State pays rent, provides public liability insurance
○ WBC holds title, but State can modify/ remodel at its own expense
○ Standard State non-assignment/ destruction/ sovereign immunity clauses
May 1998 (approximate): WBC/ SBC site lease executed
○ Begins at date of execution, terminates October 2023 (bond maturity date),
subject to early purchase option or default
○ Standard state right of entry/ destruction/ sovereign immunity clauses
○ WBC pays rent, also provides general liability insurance
May 1998 (approximate): WBC/ SBC agreement to construct executed
○ WBC= facility owner
○ SBC= general contractor & site owner

AI.WYO.GOV

■ SBC required to construct improvement on land, acquire/ install
improvements, meet completion dates, process change orders if no
material adverse effect to value
● SBC must require 1 year warranty period from subcontractors
(i.e. prime contractors)
● SBC assigns rights to proceeds from bonding claims to WBC
● SBC requires subcontractors to carry builder’s risk insurance
until WBC insures for these purposes
● WBC can enforce construction contracts if necessary
■ As consideration for improvements of prison, WBC has paid SBC
$55 million from 1998/ 2000 bonds, will pay additional $8.5 million
from 2001 bonds (but actual issue closer to $50.4 & $12.9 million)
■ SBC can request payment (if lien waiver) as project proceeds
■ If default, State consents to use of leased property as a private prison
● May/ June 1998: SBC contracts with various prime contractors executed
○ IME: $3.5 million for electrical services
○ Custom Fence: $1.3 million for fencing
○ Kloefkorn- Ballard: $ 3.4 million for general construction of admin./
warehouse buildings
○ Groathouse: $13.95 million for general construction of south facility
(including Pod A later via change order)
○ KK Mechanical: $7.95 million for mechanical work for south facility &
admin./ warehouse buildings
○ High Country Construction: $1.058 million for rough grading, dirt work,
construction of building pads/ roads
○ Mask Systems: security systems (not bid until July 1998)
● June 1998: first agreement to construct between SBC/ WBC executed
○ SBC will construct improvements/ acquire & install equipments promptly,
in exchange for payment from construction account
○ Requires performance & payment bonds from all subcontractors (i.e. prime
contractors), also contains insurance requirements
○ Pre-construction design services complete, paid from State funds but will
be reimbursed to State from portion of bond funds
● June 1998: $50.4 million in AAA-rated bonds issued to fund construction+ design
of south facility
○ Several funds created, including construction fund with project account
○ Bond issue secured by interest in leased property (total of 16 acres leased)
○ 404 bed facility of around 170,000 sq. ft.
○ All bids finalized except finish site work (security, etc.)

AI.WYO.GOV

●
●

●
●
●
●

●
●
●
●
●
●
●
●
●

●
●
●

○ No GMP set for primes’ contracts
○ SBC will use standard construction contracts, builder’s risk insurance
required
○ WBC holds general liability/ public liability insurance for leased property
○ State required to pay attorneys’ fees for certain WBC litigation
June 1998: prime contractors mobilize on site, i.e. build phase begins
July 1998: correspondence from investment bankers to A&I
○ WBC’s EIN 83-0322325 established under “governmental organization”
○ $50.4 million in tax-exempt bonds issued that month, approximately $44
million on deposit with trustee for paying construction costs, etc.
July 1998 (approximate): some (most?) piers completed at south facility
August 1998: formation of grade beam for C/D/E units
Fall 1998 (approximate): floor slabs poured/ some foundation work continues
September 1998: inter-agency A&I memo re: deductible for builder’s risk
insurance
○ appears as though State holds E&O insurance on project
○ but no reference to policy number/ insurer
October 1998: letter from Lower to LaPlante re: foundation system
○ Drilled piers used b/c shallow bedrock & expansive soil conditions
April 1999: $3.5 million in general funds appropriated (during build phase) for
taut-wire fence and re-lighting
June 1999: Plan one design contract amended for additional testing services
through Terracon (original amount maxed out)
June 2000 (approximate): legal survey/ title search conducted, no issues
August 2000: SBC contracts with Tobin for $408k in design services for CPF
facility
August 2000: south facility 98% complete, admin/ warehouse building 100%
complete
September 2000: certificate of occupancy issued for South Facility
October 2000: design stage for CPF begins, construction will begin early spring
2001, substantial completion set for April 2002
October 2000: change order log for Groathouse completed
○ Includes additional $6.5 million for Pod A construction
○ Final amount: $22 million
February/ March 2001: $9.13 million appropriated for CPF, and $994k
appropriated to rehab water service to bring new buildings online
March 2001: SBC contracts directly with Groathouse for general construction of
CPF, $8.023 million
April 2001: substantial completion of south facility

AI.WYO.GOV

● April 2001: SBC contracts directly with Terracon for soil testing/ inspection
services at CPF
● May 2001: certificate of occupancy issued for admin/ warehouse building
● May 2001: WBC/ SBC agreement to construct amended (second time) to reflect
new construction/ additional projects
● July 2001: all inmates moved from north facility, study of that facility commences
○ North facility fully vacated at this time aside from kitchen/ laundry
● December 2001: North facility study completed & presented to legislature
○ Prepared by Plan One, in association with Criminal Justice Solutions,
Rosser, Lower & Co., TST Consulting Engineers, Terracon, and
Groathouse
■ Prepared for DOC/ A&I (and ultimately legislature) to determine
whether to repair or abandon facilities
■ Looks at structural integrity, life safety, security, overall systems,
and compliance issues
○ Difficult to staff additional facility at Rawlins for projected inmate
populations
○ Numerous geo-tech & structural problems
■ Slab on grade floors in fair condition (except in mechanical rooms,
poor condition there)
■ High failure rate for buried metals (reactive soils)
■ Very poor, sometimes non-existent internal drainage systems
■ Could overall be rehabilitated with full replacement of mechanical
room slabs (including structural fill) & drainage systems
■ Significant deterioration of ceiling and floor tiling, cracked interior
masonry walls, total failure of precast exterior walls
○ Numerous code violations, window & door leaks, etc.
○ Plumbing/ HVAC/ electrical systems in fair to good condition
○ Overall poor to fair condition assessment
■ Full renovation to bring buildings up to code, etc.: $89 million
● January 2002: letters from LaPlante to Director Uphoff re: reinforcement &
structural issues at south facility
○ Lower found non-structural issues in corridors 165, 183 and cell H-130
○ LaPlante concerned about slab curl in gym (where floor is bonded to grade
beam at south end), Lower diagnoses as “differential curing strain,”
○ No major issues found with rebar/ reinforcement testing
● August 2002: certificate of occupancy issued for CPF
● August 2002: CPF opened, north facility kitchen/ laundry vacated
● January 2003: Governor Freudenthal sworn in (replaces Gov. Geringer)

AI.WYO.GOV

● December 2003 (approximate): GSG contracted for K Unit design services
● February/ March 2004 (approximate): WSP bonds paid off by State
○ State had $1.2 billion surplus in mineral tax funds at this time
● Early 2004 (approximate): design phase for K Unit begins
● May 2004: WBC registered as “inactive” with Secretary of State
● 2003 or 2004 (approximate): some windows began cracking
○ Floor slabs heaving, but superstructure not moving
● May 2008: south facility architect’s professional liability insurance expires
○ i.e. end of claim deadline under extended discovery period
○ DPIC policy no. PPL878581
● 2010 (approximate): cracks observed on exterior stucco (EFIS)
● December 2011: Gym wall stress fractures noted by WSP staff to WDOC central
office and A&I
● December 2011: structural engineer (Lower, P.C.) contacted to visit the site &
evaluate the situation
● December 2011: Lower, P.C. engineer submits site observation report to DOC
● July 2012: Lower, PC. engineer visits WSP for an additional observation of
continued cracking
● August 2012: Lower, P.C. engineer consults with Terracon engineer regarding
movement in the Gym
● August 2012: Discussions with Terracon regarding soil borings within the building
in the area of the cracking
● October 2012: Soil borings initiated inside the building
● January 2013: Terracon recommends a baseline survey for the facility to monitor
movement over time
● January 2013: Terracon Geo-tech report on October 2012 borings submitted
● January 2013: Cracking observed in the K unit (constructed in 2005-06), GSG
Architecture contacted by WSP, who then contacted the structural engineer on that
project, S.A. Miro.
● March 2013: S.A. Miro responds with findings
● May 2013: Terracon site visit to observe further cracking issues
● July 2013: Building survey plan developed
● August 2013: N.T.P. issued 8-16-13 to Coffey Engineering for WSP surveying
● September 2013: Discussion with Terracon regarding groundwater monitoring
wells
● October 2013: Terracon drilled and completed three monitoring wells at WSP
● October 2013: Design contract for drainage correction project
● December 2013: Terracon Groundwater study submitted to WDOC
● January 2014: Lower Co. submits cost estimate for drainage correction work

AI.WYO.GOV

●
●
●
●
●
●
●
●
●
●
●
●
●
●
●
●
●
●
●
●
●
●
●
●
●
●
●
●

February 2014: Bid advertisement for WSP drainage correction work
February 2014: Cracking observed in the “A” Unit area
February 2014: Terracon/lower Co. forwarded photos of cracking in area “A”
February 2014: Lower Co. scheduled for site observation of “A” unit cracking
March 2014: Coffey Engineering contract amended to continue site survey at WSP
March 2014: certain sewer lines videotaped for breaks
March 2014: Began discussion/ investigation of soil stabilization potential at WSP
March 2014: Bid results in for drainage correction work, only 1 bid
April 2014: Conference call with CST to discuss potential soil stabilization
techniques at WSP
August 2014: A Pleasant under contract for drainage correction work at WSP
August to November 2014: A Pleasant construction work proceeds on certain
courtyards/ side of facility
November 2014: Work shutdown due to winter conditions
December 2014: Wall/beam support issue identified in certain corridor
December 2014: Lower Co. site inspection of certain corridor wall/beam support
issue
December 2014: Lower Co. observation report of certain corridor issue
December 2014: Contact made with Martin/Martin Wyoming for possibility of
third party validation of what A&I/ DOC were finding at WSP
December 2014: Received design recommendations from Lower Co. regarding the
certain corridor issue
January 2015: Meeting with Martin/Martin to discuss their proposal for structural
investigation of the South Facility
January 2015: Martin/Martin engineers visited the facility for a tour of the affected
areas
February 2015: A&I requests assistance from AG representatives
February 2015: Discussion begins about destructive testing in certain areas of
WSP to determine the cause(s) of the damage
March 2015: Terracon engineers at WSP for site observations
March 2015: Martin/Martin continue to review WSP reports and documentation
April 2015: Destructive testing starts at WSP
May 2015: Discussions regarding destructive testing at WSP to include: additional
areas and selected pier testing
June 2015: Additional destructive testing at WSP
July 2015: Door & Window issues become a growing issue at the facility
July 2015: Concerns with certain control room voiced to structural engineer by J.
Heier

AI.WYO.GOV

● July to August 2015: Discussions begin with a detention contractor regarding
potential repairs to security doors and windows
● August 2015: Discussions with DOC regarding repairs to other systems,
fireproofing, etc. caused by the continued movement
● August 2015: Proposal received for door and window repair from detention
contractor. Being reviewed by DOC, A&I and State Fire Marshal’s office.
● September 2015: Additional soil samples taken from inside the facility to
determine the swell potential of the soils under the affected areas
● September 2015: Discussion and contract negotiations begin with UL regarding
door & window design & repair at WSP
● October 2015: A&I contracts with CTL Thompson for soils testing
● November 2015: Roof repairs made over the certain control room to insure roof
membrane integrity over the winter.
● November 2015: Cost Estimator engaged by Martin/Martin to establish
preliminary repair estimate for the facility
● December 2015: Martin/Martin WSP Structural report received
● December 2015: full review of 80-100 archived “bankers’ boxes (original WSP
construction/ project documents) begins
● December 2015 through January 2016: review of report by DOC and A&I.
● January 2016: Report findings to SBC. Presentation to SBC by John Lund,
Martin/Martin
● March 2016: Senate File 0091/ SEA0054 enacted (state penal facilities review)
○ Creates temporary task force to analyze/ recommend overall solutions for
WSP structural problems and related inmate housing issues.
● March 2016: Structural engineer site visits to view new areas of DOC concern
● March 2016: Discussion regarding placement of permanent survey benchmarks at
the WSP site to insure accurate survey data for ongoing monitoring of movement
● March 2016: AG’s office contracts with Martin/ Martin for non-testimonial
consulting services
● Apr. 2016: Water monitoring wells measured

AI.WYO.GOV

 

 

Prisoner Education Guide side
PLN Subscribe Now Ad 450x450
Prison Phone Justice Campaign